Example Project: PLC Controller BOM Sourcing
Challenge
A machine builder needed to source 47 line items for a production batch of PLC-based controllers with a 6-week delivery window.
Solution
Compex sourced all line items from three different global distributors, consolidated the shipment, and managed customs clearance.
Result
Full BOM delivered within the required window. All components arrived with full traceability documentation.
Example Project: ADAS Prototype Components
Challenge
An automotive tier-1 supplier needed prototype quantities of specialized automotive-grade sensors and microcontrollers.
Solution
We identified availability at OCM-authorized sources and managed the import with the required documentation for automotive traceability.
Result
Prototype components delivered for evaluation. Follow-on production volume quotation provided.
Example Project: Microcontroller Shortage Sourcing
Challenge
During an industry-wide supply shortage, a product company needed to secure stock of a specific MCU family to maintain production.
Solution
Compex identified available inventory across multiple global channels and procured verified stock with datecodes within specification.
Result
Production continuity maintained for the customer through the shortage period.
Example Project: Obsolete Component Procurement
Challenge
A defense electronics OEM required a discontinued component for a legacy system repair program.
Solution
Compex sourced original stock from specialist obsolete component brokers with full traceability and testing verification.
Result
Genuine parts sourced and delivered with traceability documentation to support the customer's quality requirements.